Developments in the Ägeri Valley

A number of infrastructure and construction projects are planned for Oberägeri. The ‘triangle’ comprising the ‘bus depot at Ländli Park – new transport interchange – flats & care centre’ presents an opportunity for the residents of Oberägeri.

 

The ZVB owns a plot of land in the centre of Oberägeri on which, amongst other things, the outdated bus depot – including staff rooms – and the Oberägeri bus stop are situated. The bus depot is outdated, lacks sufficient space and cannot be further developed.

To ensure that the ZVB can continue to fulfil its remit in future and meet the growing demand for transport, it needs a modern and larger infrastructure in the Ägeri Valley. The ‘Ländli Park’ construction project by the Ländli Foundation, which envisages integrating the bus depot, would address the ZVB’s operational requirements.

The municipality is planning a new, accessible interchange on Poststrasse, for which the ZVB is providing land. A temporary bus stop at Oberägeri station will be required during the construction period.
Provided the new interchange is built, new developments on the ZVB site will be possible.

The ZVB wishes to redevelop the central plot in line with the wishes of the local community. It is offering the local authority a section of the site for the construction of the care centre. On the remaining land, it intends to build family flats itself. The ‘triangle’ comprising the ‘bus depot in Ländli Park – interchange – flats & care centre’ presents an opportunity for the people of Oberägeri.

Dreieck mit drei Bildern zu Oberägeri

An opportunity for Oberägeri

With the triangle comprising the ‘New Bus Hub’, ‘Ländli Park’ and ‘Residential and Care Centre’, Oberägeri is undergoing development that is both forward-looking and community-focused.

Illustration von Oberägeri Zentrum

For the public

ZVB wishes to redevelop its central plot of land in the interests of the local community. It is offering the local authority a section of the site for the construction of the care centre. It intends to build family homes on the remaining land itself.

Visualisierung Busknoten Oberägeri

For passengers

The local authority is planning a new, accessible interchange on Poststrasse, for which the ZVB is providing the land.

Visualisierung Busdepot im Ländli

On behalf of the ZVB

In order for the ZVB to fulfil its remit and meet the growing demand for transport, it needs a modern and larger infrastructure. The ‘Ländli Park’ construction project, which provides for the integration of the bus depot, addresses the ZVB’s operational requirements.

Plans are being drawn up for a new bus depot

The Ländli Foundation is planning the Ländli Park project in collaboration with Zugerland Verkehrsbetriebe AG on part of its site in Oberägeri.

In Oberägeri, the Ländli Foundation is planning to build 108 affordable flats. The project also incorporates the future ZVB bus depot, which is currently located in the village centre near the ‘Oberägeri, Station’ bus stop. Relocating it to the outskirts of the village will free up valuable space for the further development of the village centre.

The architectural competition for the Ländli Park development project has been completed and the winning design was presented to the public on 5 April 2025. A decision on the development plan is expected by the end of 2026, after which the construction project will be finalised (building permit).

Further information on the Ländli Park project can be found at:

Ländli Park – Ländli Foundation

 

Pilot project

The draft masterplan is to be drawn up by the end of 2025. It sets out the infrastructure, development and use of the site and elaborates on the findings of the Ländli Park study. Aspects such as the number of buildings, spacing, open spaces, infrastructure and the feasibility of the project will be outlined.

Development plan

The local development plan sets out how the site may be developed and used. Among other things, it regulates the nature and extent of building development, construction methods, plot sizes, traffic areas and green spaces. The local development plan is expected to be finalised by mid-2027.

Construction project planning

The construction project planning phase will further flesh out the building project. It involves drawing up detailed construction plans and specifications, liaising with the relevant authorities and suppliers, preparing a cost estimate and assessing the practical feasibility of the project. The aim is to submit the planning application by the end of 2027.

Planning permission

The planning permission process is an official procedure required to obtain planning permission. It ensures that the building project complies with the applicable laws and regulations. Once this process has been completed, planning permission is expected to be granted in mid-2028.

Construction phase

The construction project is scheduled to take place between 2029 and 2031. It encompasses all activities, from preparing the building site through to the completion of the project and its handover to the client. If everything goes according to plan, all the buildings at Ländli Park will be completed and occupied by mid-2031.